Calgary and neighbouring communities are keeping water demand below the daily target of 500 million litres while work to connect the new Bearspaw South Feeder Main moves through its third week on schedule, the City of Calgary said on November 24.
Water demand on November 23 was 489 million litres, under the target the City set while the connection work is underway.
Where the work stands
At the Shaganappi Pump Station, the pipe has been connected and inspected and is ready to receive water. At 89 Street and 33 Avenue, around-the-clock construction is ongoing: crews have placed and connected the new steel T-joint that will connect the new feeder main to the existing pipe leading to the Bearspaw Water Treatment Plant, and connection work and welding continue.
At 83 Street and 33 Avenue, pipe connection work is ongoing and excavation continues to expose existing distribution pipes. The City says additional work on an existing pipe has widened the excavation area, but the work remains on schedule, and crews are planning overnight work later this week for backfilling.
Along Parkdale Boulevard and Memorial Drive N.W., pipe installation is complete at all five locations.
The City says construction continues to progress and remains on track at all worksites.
Source: City of Calgary, November 24, 2026.