The B.C. government has exempted BC Hydro’s South Peace System Reinforcement Project from requiring a certificate of public convenience and necessity, a step the province says will bring additional electricity capacity to the Dawson Creek area sooner.
The project upgrades the Dawson Creek and Bear Mountain substations so the two existing 12-kilometre, 138-kilovolt transmission lines between them can operate at 230 kilovolts, raising capacity without building new lines. BC Hydro plans to begin work in 2028, with a 2030 in-service date.
The added capacity supports NorthRiver Midstream’s proposed expansion of its West Doe Gas Plant northwest of Dawson Creek, which would raise processing capacity from 100 million to 400 million cubic feet per day at an estimated capital cost of $500 million.
The province says the West Doe expansion and other potential projects by NorthRiver, Tourmaline, ARC Resources and Shell represent as much as $3 billion in industrial investment and an estimated $8.8 billion in gross domestic product over the developments’ lifetimes.
“We’re going to double natural gas production by 2032 and triple it by 2035,” said Larry Neufeld, Minister of Energy, Mines and Petroleum Resources.
(Source: Government of British Columbia, Ministry of Energy, Mines and Petroleum Resources, news release, November 27, 2026)